Add Start Up Schedule
The Add Start Up Schedule option opens a screen to set up a schedule the report to run whenever the application server is started up.
To set up a start up schedule, complete the following steps:
-
From the left pane, select the Add Start Up Schedule button.
-
In the Name field, enter a name for the schedule.
-
Enter the Start Date and Start Time of when this report should be generated.
-
Enter the End Date and End Time of when this report cycle should stop. If these fields are left blank, the cycle will continue to run indefinitely.
-
In the Shared field, indicate whether other uses can use this same schedule for generating their reports (Yes/No). When this value is set to Yes, other users see this option when they open the Schedules tab for this report.
-
Click on the Save button to save this schedule.
Depending on the page displayed, the following fields may be available: |
The following additional section options are available in the left pane: |
Created By
The name of the user who created this report schedule.
Created On
The date this report schedule was created.
End Date
The date that the automatic report generation cycle should end. If the application server start up occurs within the time frame of the start date/start time and end date/end time, the report is generated.
End Time
The time on the End Date that the automatic report generation cycle is no longer in effect. If the application server start up occurs within the time frame of the start date/start time and end date/end time, the report is generated.
Name
The alphanumeric label identifying the schedule generation cycle.
Schedule Type
Indicates whether this report schedule should be run Once, Daily, Weekly, Monthly Days, Monthly Weeks, Startup, Immediate, or Continuous.
Shared
Indicates whether this schedule can be shared with other reports (Yes/No). When this value is set to Yes, other users can search for and use this schedule by clicking on the Add Existing Schedule button.
Start Date
The date that the automatic report generation cycle should begin. If the application server start up occurs within the time frame of the start date/start time and end date/end time, the report is generated.
Start Time
The time on the Start Date that the automatic report generation cycle becomes effective. If the application server start up occurs within the time frame of the start date/start time and end date/end time, the report is generated.